Leavenworth Road Street Project Update

3/19/2018 12:00:00 AM

Storm sewer and retaining wall installations.

The roadway contractor, Miles Excavating, has begun work and is fully underway with sotrm sewer and retaining wall installations. Activities will include the use of heavy equipment, clearing, earthwork, and trenching as well as other contractor operations as may be needed. 

NOTICE: Upcoming Road Closure beginning April 2nd, 2018 and ending on April 17th, 2018. This is the first of two 15-day closures that are needed for the project. The second 15-day road closure will occur sometime after school is out. Details on this closure are forthcoming.

Residents will be updated throughout the project and will be able to follow progress on the Leavenworth Road Project website.