Utilities that are in conflict with the proposed roadway improvements must be relocated prior to the start of roadway construction. Utility relocations are currently underway and are expected to be complete January 2018.

We woud like to thank our parterners at BPU and Capital Electric for their diligent efforts and teamwork in completnig their relocations, including the replacement of significant overhead facilities with new underground facilities, ahead of schedule.


UTILITYSTATUS
AT&TSubstantially Complete
BPU ElectricSubstantially Complete
Kansas GasSubstantially Complete
BPU WaterUnder Relocation
Spectrum CableUnder Relocation
Google FiberUnder Relocation