Call (913) 573-8620 to schedule an inspection. Please provide a 24hr notice. Your building permit number is required when scheduling an inspection.
Inspection Hours: Monday - Friday: 9:00 AM - 4:00 PM
Residential Inspection requirements:
Required for the Inspection:
Approved set of plans shall be onsite and accessible to the inspector.
Electrical, mechanical, and plumbing permits shall be onsite and accessible to the inspector.
Permit card shall be placed in an obvious location onsite and accessible to the inspector.
Complete Gas: This inspection will be conducted when all interior gas piping is installed. All installations shall be tested with a mercury gauge, or an air gauge, (marked in 2 lb. increments or smaller), and comply with chapter 12 of the Uniform Plumbing Code. (For new home construction the gas service will be inspected in the course of rough-in inspection. See item 7 this report).
Electrical Service Inspection: This inspection will be done when the meter base, overhead/underground conduit, electrical panel, main breaker, "SE" cable from meter base to the electrical panel, required grounding, and at least one branch circuit breaker and receptacle is installed. (For new home construction the electrical service will be inspected in the course of rough-in inspection. See item 7 of this report).
Temporary Electrical Power: The Board of Public Utilities (BPU) (for a fee), will supply customers with a 20-amp single-phase 120-volt service through two GFCI 20 amp receptacles, each protected by a 20-amp breaker. Call BPU at (913) 573-9831. If a 220-volt temporary service or larger is needed, a temporary electrical service permit must be obtained from this department. Requirements for overhead and underground temporary service installations are available upon request. If you have obtained a permit from our department, BPU will be contacted to set a meter when the temporary electrical service inspection has been approved.
Footing Inspection: This inspection will be conducted when all trenches, forms, and steel reinforcement bars are tied in place and properly supported.
Foundation Wall Inspection: This inspection will be conducted when all steel reinforcement bars and forms are in place. Walls shall be designed for any lateral or other loads to which they are subjected. Every effort will be made to respond within one hour of the footing/foundation inspection request.
Lath or Gypsum Board Inspection: Lath or gypsum inspections shall be made after lathing and/or gypsum board, interior or exterior, is in place, but before any plastering is applied or before gypsum board joints and fasteners are taped and finished.
Rough-In Inspections: An all-trades rough-in inspection will be conducted when all work has been completed for items A through E. The electrical service and complete gas inspections will be completed at the same time as the rough-in. (See description items 8 & 9). If the electrical service and complete gas are not ready at the time of the rough-in there will be an additional $100 fee for each inspection.
Framing: Insulation shall not be installed. Note: If construction occurs over a shallow crawl space, you should request a separate rough-in inspection prior to the installation of subfloor material, so we can verify the proper sill plate and floor joist attachment to the foundation.
Electrical All wiring and/or conduit has been installed.
Plumbing: All, water, drain, waste, vent, and gas piping has been installed.
HVAC: All duct installations are in place.
Fireplace: A fireplace inspection will be required at the time of the rough-in inspection. All factory-built fireplaces shall be listed by ICC.
Fire Resistant Assemblies: Protection of joints and penetrations in fire-resistant-rated assemblies shall not be concealed from view until inspected and approved.
Sewer Line Inspection: This inspection will be conducted by Building Inspection when the sewer line is complete from the building to the property line. The City Water Pollution Control Department requires a separate permit and inspection for the portion of the sewers located in the right of way. Call (913) 573-5400 for more information.
Water Service Line Inspection: This inspection is conducted by the Board of Public Utilities Water Department (913) 573-9622
Under-Slab Plumbing Inspection: This inspection will be conducted when all under-floor plumbing pipes are in place, but before the installation is covered with gravel, and before any concrete has been poured.
Final Inspection: Requests for a final inspection are made (24) hours in advance. No building or structure shall be occupied, and no change in the existing occupancy classification shall be made until a final inspection has been approved. A final inspection check-off list is available upon request.
Re-Inspections: Upon completion of an initial inspection an inspection slip will be left on the job site listing all violations observed. All violations must be corrected before the re-inspection request.
Re-inspection Fee: Re-inspection fees shall be assessed for each re-inspection when any portion of work itemized on the initial inspection is incomplete, or when corrections are not made. If a re-inspection is performed but the work was not corrected per the inspector's request. This fee must be paid before the scheduled re-inspection date. Fees shall be assessed as follows: Note: With each subsequent request for re-inspection this fee will increase.
$100 for the first
$150 for the second
$225 for the third
$337.50 for the fourth
All plans and construction must adhere to the 2012 International Residential Code.